Sl No. N.R.O. File No. Name of the PP Subject Area (in Hec.) Category District State Approx. Investment proposed by the PP (in Rs. In Crore) Employment likely to be generated Benefits of the project Public/Private To be felled (in No.) Compensatory Afforestation(in Hetare) Penal Compensator Afforestation (in Ha) Amount of CA (in Rs) Amount of Penal CA (in Rs) Amount of NPV (in Rs) Date of Approval (Stage I) Date of initial Receipt of proposal for final Approival in NRO Date of Receipt of proposal in this office (in complete form) for final approval No of Days Taken by State Govt. for final Approval Date of Approval (Stage II) No of Days Taken by Ad-hoc CAMPA for Confirmation No of Days Taken by N.R.O. for final Approval
Trees Plants/Poles Non Forest Land Forest Land No. of Plants Non-Forest Land Forest Land No. of Plants
1 9-HRC112-2018-CHA Gurgaon Palwal Transmission Line Diversion of 14.4543 ha (13.9978 ha in Gurugram Division and 0.4565 ha in Palwal Division) of forest land in favour of M/s Gurgaon Palwal Transmission Ltd., New Delhi for laying of 400 KV D/C HTLS Transmission Line from Prithala to Kadarpur, under forest division and distt. Gurugram and Palwal, Haryana 14.4543 Road Gurugram Haryana 81.013 9 Public Utility Public 75 9521 0 28.909 0 0 0 0 18359797 12820965 13.08.2018 19.09.2018 19.09.2018 37 03.10.2018 6 8
2 9-HRB034-2018-CHA PWD Ambala Diversion of 0.67 ha of forest land in favour of SDE, PWD B&R Sub Division, Shahzadpur for construction of road on Tangri Bundh from Gazipur road to Fatehgarh road, km. 0-0.800 under forest division and distt. Ambala, Haryana. 0.67 Road Ambala Haryana 0.135 9 Public Utility Public 108 0 0 1.34 0 0 0 0 999077 594290 15.05.2018 03.10.2018 03.10.2018 141 05.10.2018 1 1
3 9-HRB083-2018-CHA PWD Karnal Diversion of 4.875 ha of forest land in favour of Executive Engineer, Provincial division No. 2, PWD B&R Karnal for 4 laning of Safidon-Assandh-Kaithal road from RD 158.300 to 159.970 and 160.220 to 162.300, under forest division and Distt Karnal, Haryana. 4.875 Road Karnal Haryana 3.591 20 Public Utility Public 382 0 0 9.75 0 0 0 0 7183550 4324125 06.06.2018 03.10.2018 03.10.2018 119 05.10.2018 1 1
4 9-HRB092-2018-CHA PWD Karnal Diversion of 0.656 ha of forest land in favour of Executive Engineer, Provincial division No.1, PWD B&R Br., Karnal for widening and strengthening of Karnal-Kachhwa-Sambhli-Kaul road from RD 21.680 to 26.580, under forest division and distt Karnal, Haryana. 0.656 Road Karnal Haryana 0.34 20 Public Utility Public 67 0 0 1.312 0 0 0 0 979645 581872 28.05.2018 03.10.2018 03.10.2018 128 05.10.2018 1 1
5 9-HRC118-2018-CHA NHAI Jhajjar and Bhiwani Diversion of 36.6928 ha (3.349 ha in Jhajjar Division and 33.3438 ha in Bhiwani Division) of forest land in favour of Project Director, NHAI, PIU, Rohtak for redesigning, rehabilitation and upgradation to 2 lane with paved shoulder configuration & strengthening of Jhajjar-Loharu section of new NH 334 B from design km 0.00 (existing km 130.770 of SH 20) to design km 97.860 (existing km 228.630 of SH 20), under forest division and distt. Jhajjar and Bhiwani, Haryana 36.6928 Road Jhajjar and Bhiwani Haryana 23.2 100 Public Utility Public 12402 12222 0 73.378 0 0 0 0 62159093 29575950 06.09.2018 04.10.2018 04.10.2018 28 08.10.2018 1 3
6 9-HRC128-2018-CHA NHAI Rohtak Diversion of 41.331 ha of forest land in favour of Project Director, NHAI, PIU, Rohtak for rehabilitation and upgradation to 2 lane with paved shoulder for Jind-Karnal section from existing chainage 68.660 to 153.700 on NH 709A, (Package-II), under forest division and District Karnal, Haryana 41.331 Road Rohtak Haryana 42.036 100 Public Utility Public 4357 23839 0 82.622 0 0 0 0 84722251 36660597 13.08.2018 04.10.2018 04.10.2018 52 08.10.2018 1 3
7 9-HRC129-2018-CHA NHAI Rohtak Diversion of 69.7131 ha (46.2094 ha in Sonipat Division+ 6.4025 ha in Rohtak Division+ 17.101 ha in Jhajjar Division) of forest land in favour of Project Director, NHAI,PIU, Rohtak for redesigning, rehabilitation and upgradation to 4 lane configuration & strengthening of UP/Haryana Border-Sonipat-Rohtak-Jhajjar (from km 0 to 80.250) section of new NH 334B in the State of Haryana, under forest division and District Sonipat, Rohtak and Jhajjar, Haryana 69.7131 Road Jhajjar Haryana 0.28 100 Public Utility Public 9350 11164 0 139.426 0 0 0 0 139781898 3188310 13.08.2018 04.10.2018 04.10.2018 52 09.10.2018 3 2
8 9-HRC110-2018-CHA Tr Line Gurgaron Diversion of 14.1266 ha of forest land in favour of Gurgaon Palwal Transmission Ltd. For laying of 400 KV D/C HTLS transmission line from Kadarpur to Sohna, under forest division and distt. Gurugram, Haryana 14.1266 Tr Line Gurugram Haryana 0.28 100 Public Utility Public 50 10432 0 28.253 0 0 0 0 17669427 12530294 13.08.2018 01.10.2018 01.10.2018 49 11.10.2018 3 4
9 9-HRB028-2018-CHA Excelsior American School Diversion of 0.0228 ha of forest land for access to Excelsior American school by Shankuntla Devi Educational Society along Chakarpur Bundh RD 8-9 L/s at vllage Wazirabad, under forest diviion and distt. Gurugram, Haryana. 0.0228 Approach Gurugram Haryana 0.15 60 Public Utility Private 0 0 0 0.05 0 0 0.5 0 24100 241000 22555 16.02.2018 19.06.2018 03.10.2018 229 11.10.2018 5 3
10 9-HRB054-2018-CHA Aarsh Sahitya Prachar Trust Diversion of 0.056 (instead of 0.0309 ha) of forest land for access to Private Land situated in village Nolta, Tehsil-Kalka, under forest division Morni-Pinjoreand distt. Panchkula, Haryana. 0.056 Approach Panchkula Haryana 0.045 8 Public Utility Private 2 0 0 0.112 0 0 0.5 0 11847 574235 49672 09.08.2018 20.09.2018 17.10.2018 69 23.10.2018 3 3