Sl No. N.R.O. File No. Subject Cate-
gory
Area (in Hec.) To be felled (in No.) Compensatory Afforestation(in Hetare) Penal Compensator Afforestation (in Ha) Amount of CA (in Rs) Amount of Penal CA (in Rs) Amount of NPV (in Rs) Date of Approval (Stage I) Date of initial Receipt of proposal for final Approival in NRO Date of Receipt of proposal in this office (in complete form) for final approval No of Days Taken by State Govt. for final Approval Date of Approval (Stage II) No of Days Taken by Ad-hoc CAMPA for Confirmation No of Days Taken by N.R.O. for final Approval
Trees Plants
/Poles
Non Forest Land Forest Land No. of Plants Non-Forest Land Forest Land No. of Plants
1 9-PBB607-2013-CHA Diversion of 3.75 hectare of forest land for construction of ROB in lieu of level crossing 15-C Km 22/8-9 on Rajpura Bhatinda Rail Section on Northern Bypass Patiala under Forest Division and District Patiala Punjab Road 3.75 367 440 0 7.50 0 0 0 0 1526190 0 3326250 30.10.2013 23.01.2014 23.01.2014 85 04.02.2014 3 9
2 9-PBB579-2011-CHA Diversion of 0.9211 hectare of forest land for construction of High Level Bridge over Satluj river industry approaches crossing Ludhiana Rahon at Garhi Fazil Forest & Dushai Bandh road 14.5 to 149 B/s under Forest Division and District Ludhiana, Punjab Others 0.9211 57 1200 0 2.303 0 0 0 0 410733 0 817016 05.12.2013 27.04.2012 27.04.2012 843 03.02.2014 2 0
3 9-PBB645-2013-CHA Diversion of 1.7505 hectare of forest land in favour of PWD B&R for widening and strengthening of Patiala Bhadson road, RD 4.14 to 8.00 kms, B/ s under Forest Division & District Patiala, Punjab. Road 1.7505 1580 0 0 3.501 0 0 0 0 712426 0 1552694 20.11.2013 29.01.2014 29.01.2014 70 05.02.2014 3 2
4 9-PBB171-2013-CHA "Diversion of 0.0812 hectares of forest land in favour of PWD (B&R) for construction of High Level Bridge on Chakki River Mirthal Abadgarh to Jalandhar-Pathankot road Kms 88-88.040, R/s under Forest Division and District Gurdaspur, Punjab" Road 0.0812 21 0 0 0.21 0 0 0 0 109877 0 72024 02.05.2013 31.01.2014 31.01.2014 274 07.02.2013 1 6
5 9-PBB287-2013-CHA Diversion of 0.0079 hectares of forest land in favour of Shri Sanjeev Kumar Adlakha for construction of approach road to Show Room at village PANGOLI on Mamoon to Madhopur road, Kms 5-6, Lis under Forest Division, District Pathankot, Punjab. Other 0.0079 4 0 0 0.04 0 0 0 0 20929 0 7007 12.07.2013 16.08.2013 06.02.2014 209 10.02.2014 3 2
6 9-PBB647-2013-CHA Diversion of 0.0396 hectares of forest land in favour of PSPCL for erection of 66 KV Bhawanigarh 220 KV BBMB Sangrur SC/DC Tower Line under Forest Division and District Sangrur, Punjab Tr. Line 0.0396 27 0 0 0.27 0 0 0 0 24790 0 58358 08.11.2013 31.01.2014 31.01.2014 84 11.02.2013 0 11
7 9-PBC630-2013-CHA Diversion of 11.534 hectares (6.604 ha+4.93 hal of forest land in favour of PWD (B&R) for construction of ROB, beautification and four laining/widening of Amritsar-Taran-Taran road, NH-15/34, Kms 110.25 to 114.200, B/s and four laining/widening of Amritsar-Pathankot-Kandal road alongwith service road on both sides from Kms 102.900 to 106.420, NH-15/34 Section (Verka Chowk by pass to Celebration Mall) under Forest Division & District, Amritsar, Punjab. Road 11.534 494 400 0 23.3 0 0 0 0 12151089 0 9261802 03.01.2014 21.01.2014 07.02.2014 35 14.02.2014 1 6
8 9-PBB406-2014-CHA Diversion of 0.003052 hectare of forest land in favour of MIs Bharat Petroleum Corporation Limited for construction of approach road to setting up of retail outlet at village JALALPUR, Tehsil-Derabassi on Lehli-Banur road KM 2-3 RIS under Forest Division and District S.A.S. Nagar, Punjab Retail Outlet 0 0 0 0 0.008 0 0 0 0 2425 0 1911 27.01.2014 04.02.2014 04.02.2014 6 14.02.2014 6 5
9 9-PBB180-2013-CHA "Diversion of 0.01847 hectares (instead of 0.05374 hectares) of forest land in favour of M/s PMC Entertainment Pvt. Ltd for construction of approach road to FORTUNE COUNTRY, Residential Colony at village BONKER DOGRAN and MAJARA KHURD on GT road (NH-l), Kms 327328, L/s under forest division, district Ludhiana, Punjab." Others 0.05374 9 0 0 0.047 0 0 0 0 14452 0 11562 30.10.2013 14.02.2014 14.02.2014 107 20.02.2014 0 6
10 9-PBB281-293-610-2013-CHA "Diversion of 4.3952 hectares (i.e 0.4876 ha Patiala Forest Division+0.9706 ha S.A.S. Nagar Forest Division+1.7020 ha in Ludhiana Forest Division+1.2350 ha in Jalandhar Forest Division) of forest land in favour of PSTCL for construction of transmission line from 400 KV SIS ~jpura to proposed 400 KV SIS Nakodar under Forest DivisioD,s and Districts of Patiala, SAS Nagar, Ludhiana and Jalandhar respectively of Punjab State" Tr. Line 1.7020 405 213 0 3.404 0 0 1.352 0 258435 35102 432501 24.10.2013 29.11.2013 10.02.2014 109 20.02.2014 2 8
11 9-PBB660-2012-CHA "Diversion of 0.0124 hectares (instead of 0.0180 hectares) of forest land in favour of M/ s Indian Oil Corporation Limited for approach road to retail outlet at Village DATEWAS on Jhakhal-Budhlada Road, Kms 3132, L/S under Forest Division & District Mansa, Punjab" Others 0.018 0 0 0 0.045 0 0 0 0 0 0 11268 16.10.2012 28.11.2013 14.02.2014 78 20.02.2014 1 5